After enabling costings in Indigo settings, you can calculate the values of allocated shifts in your scheduler.

To calculate shift values in your scheduler:

  1. In the left sidebar of Indigo, click Time and Attendance.
  2. In the Main section, click on Scheduler.
  3. Click on Calculate cost in the far-right end of the toolbar.

Calculating costs only applies to the week currently in view in the scheduler. Go to other weeks in your scheduler and click Calculate cost to get the values for those shifts and rosters.

After initially calculating the costs for a particular week, any cost adjustments will be automatically done when you make modifications to that week. Each week needs to be calculated individually before auto-calculations can be done.

Allow the system time to calculate costs. Do not exit from the scheduler before cost calculations finishes.

After calculating costs in your scheduler, you can: